Alki Elementary School Addition and Gym Modernization Project

Alki小学临时校址

Alki Elementary School has relocated to the Schmitz Park School interim site for the 2023-24, 2024-25, 2025-26学年.

地址:5000 SW Spokane Street

项目简介

现有的Alki小学大部分将被拆除. 多层75,000 square foot replacement school will be constructed and the existing gymnasium will remain and be modernized. The existing Seattle Parks department community center will remain.

Funding: This project is funded by the Building Excellence V Capital Levy (BEX V), 西雅图选民在2019年通过的法案.

专为当前和未来的学生

The new Alki will provide an equitable learning environment for up to 500 K-5 students with inclusive spaces to support its diverse community of students and families. The facility will be constructed of materials and systems that will stand the test of time and  last 75 years or more.

The new building will meet district educational standards for elementary schools, 根据Alki社区的具体需求进行调整. Input gathered from the 学校设计谘询小组(SDAT) — an advisory group consisting of school leaders, students, parents, and community members — ensures that the design reflects and honors the school personality, identity, and society

The design puts a priority on being easy to navigate for students, staff, and parents. It includes an inviting “front porch” at the new entrance facing the park boulevard, 如何加强与社区和公园的联系.

安全与保障

Visitors will enter through a secure main entrance that invites you into the administrative office for check-in before entering the school. 在上学期间,所有其他的门都将被锁上.

Sustainability

The new Alki Elementary is being designed to work toward the district’s goals for clean energy and renewable resources and includes the installation of solar panels.

该项目将包括:

  • 所有教室和学习空间都有日光
  • 高效采暖,通风新鲜

建筑材料包括交叉层压木材(CLT), a material that reduces the carbon footprint of the whole project.

The Energy Use Index (EUI) for the project is pending with a goal of 15-18.

Timeline

construction phase graphic showing that the school is in the Construction phase
了解在这些项目阶段会发生什么
  • 预设计阶段完成
  • 方案设计阶段完成
  • 设计开发阶段完成
  • 施工文件/许可阶段正在进行中
  • Bid and award phase in progress for rebidding selected bid packages
  • 早期建设活动正在进行中
  • 计划开学时间:2026年9月

项目进展

Photos

exterior of a 2 story brick building has a person on a lift wearing a mask and removing material from a window frame
Hazardous materials abatement of the old windows – August 2023
an excavator is crushing a wooden building while a person sprays a hose at it
Demolition of the portable with dust control with hose – August 2023
一台挖掘机正在碾压一座砖砌建筑. 电梯上有一个人在喷水管. 前景的混凝土上有碎石
主楼拆除,向东- 2023年8月
an excavator is on top of a pile of concrete rubble emptying into a container on a truck
分离和清除拆除碎片- 2023年8月
铲土机正在拆除建筑物的地板
拆除露出了旧地板的一部分. 2023
一幢两层楼房前的一块分级土地
9月,学校场地清理完毕,朝向体育馆. 2023
建筑物的外部,工人在电梯上
Sealing and protecting the existing gym after the school building was removed – Sept. 2023
2 workers in construction vests and hats hold hoses while standing in a dirt field. 这块地有一部分是绿色的.
Installing hydroseed to protect the site during the construction pause – Oct. 2023
一个开放的区域有草地和橙色的临时织物栅栏
水培草有助控制径流- 11月. 2023
一座两层楼建筑附近的草地上有一个池塘. 可以看到一个橙色的建筑围栏.
Temporary erosion control working to avoid run-off of rain water – Dec. 2023
Aerial view of a large lot with ponding and grass next to a building
Current conditions with grass and temporary erosion control to keep water out of the building – Jan. 2024

Project Update

March 2024

This month, the contractor will resume construction on the retaining and shoring wall at the southeast corner of the project site. The permit for this work was issued by Seattle Department of Construction and Inspections (SDCI) in August 2023. 由于冬季天气潮湿,工作暂停了.

工作内容包括:

  • 临时侵蚀控制措施.
  • 发掘过程中的文化资源监测.
  • 清理现有景观.
  • 准备挡土墙/支撑墙.
  • 筑挡土墙/支撑墙.
  • 雨水拱顶的开挖.
  • 挡土墙/支撑墙的回填土.
  • Other work as needed for this permitted portion of the project.

Schedule:

  • 3月18日至3月31日:景观清理和准备工作.
  • 4 - 5月:建造挡土墙.

离职程序仍在进行中. School building construction cannot begin until the Departures process is complete and a building construction permit is issued. Alki Elementary School is still expected to reopen for Fall of 2026.

Current Designs

下面的图纸显示了学校目前的设计.

drawing of an aerial view of a large building with a mechanical penthouse. a space above it has colored blobs on it and is marked "parkway." Beyond that, a the top of the image is an area marked Seattle Parks and Rec Alki Playground
计划中的学校的建筑师图纸- 2023年6月
architect drawing of a 3 story brick building corner with a breeze way entrance to the left
学校西侧的潜在景观
architects drawing of a 3 story brick building with windows and doors on ground floor and a paved area with people in front
欢迎进入的潜在视图
architect drawing of a person standing in front of a whilte board with younger people sitting at tables
学习区域的潜在视图
architect drawing of people sitting in front of a wall of windows
库窗口的潜在视图
architect drawing of a large space with a door and a stairway
可以看到中央楼梯
建筑师绘制的带有午餐桌的大空间图
公共/用餐区的潜在景观
an architects drawing of a classroom with an adult and a child at a white board
潜在的教室

社区参与

The 基本建设项目及规划 department values insight and input from the school community and neighbors when planning a construction project, beginning with the 学校设计谘询小组(SDAT) process.

使用多种工具,包括电子邮件, mail, flyers, posters, signage, 社区会议, 以及项目网页. Summary of all communication and engagement during the Alki Elementary School planning process.

学校设计谘询小组(SDAT)

在设计过程的早期, representatives from the school community come together to form a school’s SDAT. SDATs typically include school and district staff, parents, and community members. Students are sometimes included for all or part of the process. 项目施工经理也参与其中. 了解更多关于Alki小学SDAT的信息.

Project Team

Design Firm: Mahlum建筑师

总承包商/建筑管理公司(GC/CM): 基石总承建商

Project Manager:布莱恩·法贝拉, brfabella@tricitiesstrikers.com, 206-252-0702